Report: Nuke dump radiation leak could have been prevented
The Washington Post
 

Report: Nuke dump radiation leak could have been prevented
The Washington Post
April 16, 2015
LINK
 
ALBUQUERQUE, N.M. — A radiation leak that forced the indefinite closure of the federal government’s only underground nuclear waste repository could have been prevented, a team of investigators said Thursday.
 
A combination of poor management, lapses in safety and a lack of proper procedures were outlined in a final report released by the U.S. Department of Energy’s Accident Investigation Board. Officials reviewed the findings Thursday night during a community meeting in Carlsbad.
 
The investigators spent more than a year looking into the cause of the radiation release at the Waste Isolation Pilot Plant in southeastern New Mexico.
 
Like a separate team of technical experts, they too found that a chemical reaction inside a drum of waste that had been packaged at Los Alamos National Laboratory forced the lid open, allowing radiation to escape. The contents included nitrate salt residues and organic cat litter that was used to soak up moisture in the waste.
 
Aside from lab managers, the report places blame on Energy Department headquarters, the National Nuclear Security Administration and the Nuclear Waste Partnership, the contractor that manages the repository. It highlights numerous failures — from Los Alamos lab not having an adequate system for identifying and controlling hazards to federal nuclear officials not ensuring the existence of a “strong safety culture” at the lab.
 
Investigators found a failure by managers to resolve employee concerns that could have pointed out problems before the waste was shipped from Los Alamos to the repository.
 
Accident Investigation Board Chair Ted Wyka said during the town hall that some workers reported seeing foaming and yellowish smoke while repackaging waste. After short discussions with their supervisors, they went back to work on the assembly line.
 
That information did not make it up to lab managers, he said.
 
“It wasn’t an issue of malice,” Wyka said. “It was more of an issue of just not understanding ... the issue, the reactions that they were working with, the hazards involved and the controls.”
 
Lab Director Charlie McMillian acknowledged in a staff memo obtained by The Associated Press that investigators pointed out “serious deficiencies” in the lab’s processes and procedures.
 
“We now know from the investigations that if (Los Alamos National Laboratory) had followed certain basic steps, this event would not have happened. Also, if we had complied with our hazardous waste permit, we would have avoided the serious legal and credibility issues we now face,” McMillian wrote.
 
The Energy Department and its contractors are facing $54 million in fines from the state of New Mexico for the failures that led to the mishap. Negotiations are ongoing, and the state has suggested more financial penalties are possible.
 
With the repository closed indefinitely, efforts to clean up decades of Cold War-era waste at federal facilities around the country are stalled. Federal officials say resuming full operations at the repository could take years and cost more than a half-billion dollars.
 
David Klaus, the Energy Department’s deputy under secretary for management and performance, said the agency is working on corrective actions to ensure greater oversight of the disposal of radioactive waste.
 
The full report can be found here.
More Information
 
 
 
 
 
To help ensure that you receive all email with images correctly displayed, please add ecabulletin@aweber.com to your address book or contact list  
to the ECA Email Server
If you have trouble viewing this email, view the online version
 
May 18-19

Los Alamos Peer Exchange
July 16-17


Events of Interest
 

House Energy and Water Appropriations Markup of Spending Bill
Week of April 20 or 27

Commission to Review the Effectiveness of the National Energy Labs Meeting
April 22

Senate Strategic Forces Subcommittee hearing on Nuclear Enterprise Review Recommendations
April 22

Environmental Management SSAB Chairs Meeting
April 22-23

House Strategic Forces NDAA Markup
April 23

NNSA Challenges Ahead: Meeting Nuclear Deterrent Requirements
April 24

Northern New Mexico SSAB Meeting
May 13

Oak Ridge SSAB Meeting
May 13